Development of Lok Ma Chau Loop: Main Works Package 1 - Contract 1 Site Formation and Infrastructure Works inside Lok Ma Chau Loop and Western Connection Road Phase 1 (Contract No. YL/2020/01)

Client

The Government of the Hong Kong Special Administrative Region (CEDD West Development Office)


Period

Jul 2021 - Now

1041 and 1050

The works to be executed under this contract involve:
- ground treatment and site formation works of about 75 hectares within the Lok Ma 
Chau Loop (the Loop);
- construction of about 3,000-metre-long carriageway and associated footpaths and 
cycle tracks, and a public transport interchange, within the Loop;
- construction of Western Connection Road Phase 1 through widening of the 
existing Ha Wan Tsuen East Road of about 800m long; associated ground 
treatment and site formation works; construction of footpath, cycle track, slopes 
and retaining walls; and construction of a bridge about 60m long over the old 
Shenzhen River meander;
- provision of other infrastructure, including a tertiary sewage treatment works and 
sewerage system, a water supply system and a drainage system, and other 
associated works; and 
- environmental mitigation measures including compensation for offsite wetland of 
about 18 ha and offsite woodland of about 1.3 ha.