Superstructure Works for the Proposed Composite Development at Yuet Wah Street and Hip Wo Street, Kwun Tong

Construction of one luxury residential tower with a total of 299 domestic units on top of transfer plate and 4-levels podium which comprise of clubhouse on podium garden and 3-levels for Government Accommodation Areas ("GIC") including pedestrian link and I-basement level carpark with a total approximate GF A of 299, 562 ft2. The development is of reinforced concrete construction completed with precast facade, loss form, finishes, building services and ancillary works. The works also include construction of substructure works and underground drainage works.

Client
Central Wisdom Limited

Contract Value
541 million HKD

Construction Period
April 2012 - June 2014